-\section{Daily News}
+\part{Daily News for the Operator}
-\textbf{2022/01/31 - this page will be updated during the beamtime}
+\textbf{2022/02/03 - this page will be updated during the beamtime}
\begin{itemize*}
- \item Nothing to report, yet.
+ \item Always keep an eye on the rate plots (``Main Screen 4'' on the web page). If you notice any
+asymmetry between sectors / parts of detectors, try to do a reload of thresholds for the detector
+(do a ``Start Stop DAQ'' before and after to avoid taking corrupted data). If this doesn't help,
+talk to the detector expert, e.g. a power cycle of the frontends might be necessary.
+
+ \item Every 1 to 2 hours, when you do a DAQ restart, please do a ``Start Stop Trigger'', ``Reboot
+DiRich'' and a ``Reboot ECal'' before.
\end{itemize*}
\clearpage
-
+\part{General Advice}
\section{Main Tasks}
\begin{itemize*}
\item Operate the data acquisition, mainly using the
\item Make entries to the logbook about configuration changes and important issues.
\end{itemize*}
-\subsection*{DAQ Shifts}
+\section{DAQ Shifts}
\begin{itemize*}
\item Please make sure your first shift is one of the day shifts, not a night shift. During the
day availability of experts is better, so you can get more help.
\section{Full Power Cycle / Daily DAQ reboot}
This should be performed at least once a day, when there is a break of ~ 15 minutes and in presence
of the DAQ expert: {\bf To be updated for 2022!}
-% \begin{enumerate}
-% \item MDC power supply group off (EPICS)
-% \item RICH power supply group power cycle (EPICS) \\
-% Main power supply group power cycle (EPICS)
-% \item ECAL Padiwa Powercycle \\
-% Start Powercycle \\
-% CentralControls Powercycle \\
-% iTof Powercycle \\
-% Hodo Powercycle
-% \item Reprogram FPGA \\
-% BLR Reload Settings
-% \item Start DAQ (x2, because of MDC Hubs)
-% \item MDC power supply group on (EPICS)
-% MDC LV Turn On All Relais
-% \item Reboot OEP
-% \item Start DAQ
+\begin{enumerate}
+\item Switch off beam on control panel
+\item MDC power supply group off (EPICS)
+\item ECAL Padiwa Powercycle \\
+ Hodo
+ Start Powercycle \\
+ STS Fee \\
+ iTof Powercycle \\
+ Triggerbox Beam \\
-% \end{enumerate}
+\item RICH power supply group power cycle (EPICS) \\
+ Main power supply group power cycle (EPICS)
+
+\item Reprogram FPGA \\
+ BLR Reload Settings
+\item Start DAQ (x2, because of MDC Hubs)
+\item MDC power supply group on (EPICS)
+ MDC LV Turn On All Relais
+\item Reboot OEP
+\item Start DAQ
+\item Load ECal Thresholds
+\item Check Eventbuilders getting data / all boards have IPs
+\item Switch on beam
+\end{enumerate}